[eu]cite

Home› Civil Code & Private Law› BGB (EN)

Book 2 · Law of obligations  ›  Chapter 1 · General provisions › Section 646

Completion in lieu of acceptance

If acceptance is excluded due to the nature of the work, then, in the cases governed by sections 634a (2) and 641, 644 and 645, completion of the work takes the place of acceptance.

←→ also move between sections