Ineffectiveness of the specification; substitution

(1) If the third party is to specify performance at its reasonably exercised discretion, then the specification made will not be binding on the contracting parties if it is evidently inequitable. The specification is made in this case by judicial decision; the same applies if the third party cannot or does not want to make the specification or if it delays it.

(2) If the third party is to make the specification at its free discretion, the contract is ineffective if the third party cannot or does not want to make the specification or if it delays it.