[eu]cite

Home› Civil Code & Private Law› BGB (EN)

Book 2 · Law of obligations  ›  Chapter 1 · General provisions › Section 635

Cure

(1) If the customer demands cure, then the contractor may, at their option, remedy the defect or produce a new work.

(2) The contractor is to bear the expense necessary for cure, in particular transport, workmen’s travel, work and materials costs.

(3) The contractor may refuse cure, without prejudice to section 275 subsections (2) and (3), if it is possible only at disproportionate cost.

(4) If the contractor produces a new work, they may demand from the customer return of the defective work in accordance with sections 346 to 348.

←→ also move between sections