Chapter 3 · Capacity allocation and congestion management cost recovery › Article 79

Costs of ensuring firmness

The costs of ensuring firmness in accordance with Articles 70(2) and 71 shall be borne by the relevant TSOs, to the extent possible in accordance with Article 16(6)(a) of Regulation (EC) No 714/2009. These costs shall include the costs from compensation mechanisms associated with ensuring the firmness of cross-zonal capacities as well as the costs of redispatching, countertrading and imbalance associated with compensating market participants.