Chapter 1 · Capacity calculation  ›  Section 2 · The common grid model › Article 17

Common grid model methodology

1.   By 10 months after the entering into force of this Regulation all TSOs shall jointly develop a proposal for a common grid model methodology. The proposal shall be subject to consultation in accordance with Article 12.

2.   The common grid model methodology shall enable a common grid model to be established. It shall contain at least the following items:

(a)

a definition of scenarios in accordance with Article 18;

(b)

a definition of individual grid models in accordance with Article 19;

(c)

a description of the process for merging individual grid models to form the common grid model.