1. In order to produce results, the price coupling algorithm shall use:
(a)
allocation constraints established in accordance with Article 23(3);
(b)
cross-zonal capacity results validated in accordance with Article 30;
(c)
orders submitted in accordance with Article 40.
2. The price coupling algorithm shall produce at least the following results simultaneously for each market time unit:
(a)
a single clearing price for each bidding zone and market time unit in EUR/MWh;
(b)
a single net position for each bidding zone and each market time unit;
(c)
the information which enables the execution status of orders to be determined.
3. All NEMOs shall ensure the accuracy and efficiency of results produced by the single price coupling algorithm.
4. All TSOs shall verify that the results of the price coupling algorithm are consistent with cross-zonal capacity and allocation constraints.