[eu]cite

Home› Energy & Climate› CACM Guideline Regulation

Chapter 1 · Capacity calculation  ›  Section 3 · Capacity calculation methodologies › Article 25

Methodology for remedial actions in capacity calculation

1.   Each TSO within each capacity calculation region shall individually define the available remedial actions to be taken into account in capacity calculation to meet the objectives of this Regulation.

2.   Each TSO within each capacity calculation region shall coordinate with the other TSOs in that region the use of remedial actions to be taken into account in capacity calculation and their actual application in real time operation.

3.   To enable remedial actions to be taken into account in capacity calculation, all TSOs in each capacity calculation region shall agree on the use of remedial actions that require the action of more than one TSO.

4.   Each TSO shall ensure that remedial actions are taken into account in capacity calculation under the condition that the available remedial actions remaining after calculation, taken together with the reliability margin referred to in Article 22, are sufficient to ensure operational security.

5.   Each TSO shall take into account remedial actions without costs in capacity calculation.

6.   Each TSO shall ensure that the remedial actions to be taken into account in capacity calculation are the same for all capacity calculation time-frames, taking into account their technical availabilities for each capacity calculation time-frame.

←→ also move between articles