[eu]cite

Home Energy & Climate ACER Regulation (recast)

Chapter I · Objectives and tasks › Article 5

Tasks of ACER as regards the development and implementation of network codes and guidelines

1.   ACER shall participate in the development of network codes in accordance with Article 59 of Regulation (EU) 2019/943 and Article 6 of Regulation (EC) No 715/2009 and of guidelines in accordance with Article 61(6) of Regulation (EU) 2019/943 It shall in particular:

(a)

submit non-binding framework guidelines to the Commission where it is requested to do so under Article 59(4) of Regulation (EU) 2019/943 or Article 6(2) of Regulation (EC) No 715/2009. ACER shall review the framework guidelines and re-submit them to the Commission where requested to do so under Article 59(7) of Regulation (EU) 2019/943 or Article 6(4) of Regulation (EC) No 715/2009;

(b)

provide a reasoned opinion to the ENTSO for Gas on the network code in accordance with Article 6(7) of Regulation (EC) No 715/2009;

(c)

revise the network code in accordance with Article 59(11) of Regulation (EU) 2019/943 and Article 6(9) of Regulation (EC) No 715/2009. In its revision, ACER shall take account of the views provided by the parties involved during the drafting of that revised network code led by the ENTSO for Electricity, the ENTSO for Gas or the EU DSO entity, and shall consult the relevant stakeholders on the version to be submitted to the Commission. For this purpose, ACER may use the committee established under the network codes where appropriate. ACER shall report to the Commission on the outcome of the consultations. Subsequently, ACER shall submit the revised network code to the Commission in accordance with Article 59(11) of Regulation (EU) 2019/943 and Article 6(9) of Regulation (EC) No 715/2009. Where the ENTSO for Electricity, the ENTSO for Gas or the EU DSO entity have failed to develop a network code, ACER shall prepare and submit a draft network code to the Commission where it is requested to do so under Article 59(12) of Regulation (EU) 2019/943 or Article 6(10) of Regulation (EC) No 715/2009;

(d)

provide a duly reasoned opinion to the Commission, in accordance with Article 32(1) of Regulation (EU) 2019/943 or Article 9(1) of Regulation (EC) No 715/2009, where the ENTSO for Electricity, the ENTSO for Gas or the EU DSO entity has failed to implement a network code elaborated under point (a) of Article 30(1) of Regulation (EU) 2019/943 or Article 8(2) of Regulation (EC) No 715/2009 or a network code which has been established in accordance with Article 59(3) to (12) of Regulation (EU) 2019/943 and Article 6(1) to (10) of Regulation (EC) No 715/2009 but which has not been adopted by the Commission under Article 59(13) of Regulation (EU) 2019/943 and under Article 6(11) of Regulation (EC) No 715/2009.

(e)

monitor and analyse the implementation of the network codes adopted by the Commission in accordance with Article 59 of Regulation (EU) 2019/943 and Article 6 of Regulation (EC) No 715/2009 and the guidelines adopted in accordance with Article 61 of Regulation (EU) 2019/943, and their effect on the harmonisation of applicable rules aimed at facilitating market integration as well as on non-discrimination, effective competition and the efficient functioning of the market, and report to the Commission.

2.   Where one of the following legal acts provides for the development of proposals for common terms and conditions or methodologies for the implementation of network codes and guidelines which require the approval of all regulatory authorities, those proposals for common terms and conditions or methodologies shall be submitted to ACER for revision and approval:

(a)

a legislative act of the Union adopted under the ordinary legislative procedure;

(b)

network codes and guidelines adopted before 4 July 2019 and subsequent revisions of those network codes and guidelines; or

(c)

network codes and guidelines adopted as implementing acts pursuant to Article 5 of Regulation (EU) No 182/2011 of the European Parliament and of the Council (20).

3.   Where one of the following legal acts provides for the development of proposals for terms and conditions or methodologies for the implementation of network codes and guidelines which require the approval of all the regulatory authorities of the region concerned, those regulatory authorities shall agree unanimously on the common terms and conditions or methodologies to be approved by each of those regulatory authorities:

(a)

a legislative act of the Union adopted under the ordinary legislative procedure;

(b)

network codes and guidelines that were adopted before 4 July 2019 and subsequent revisions of those network codes and guidelines; or

(c)

network codes and guidelines adopted as implementing acts pursuant to Article 5 of Regulation (EU) No 182/2011.

The proposals referred to in the first subparagraph shall be notified to ACER within one week of their submission to those regulatory authorities. The regulatory authorities may refer the proposals to ACER for approval pursuant to point (b) of the second subparagraph of Article 6(10) and shall do so pursuant to point (a) of the second subparagraph of Article 6(10) where there is no unanimous agreement as referred to in the first subparagraph.

The Director or the Board of Regulators, acting on its own initiative or on a proposal from one or more of its members, may require the regulatory authorities of the region concerned to refer the proposal to ACER for approval. Such a request shall be limited to cases in which the regionally agreed proposal would have a tangible impact on the internal energy market or on security of supply beyond the region.

4.   Without prejudice to paragraphs 2 and 3, ACER shall be competent to take a decision pursuant to Article 6(10) where the competent regulatory authorities fail to agree on terms and conditions or methodologies for the implementation of new network codes and guidelines adopted after 4 July 2019 as delegated acts, where those terms and conditions or methodologies require the approval of all the regulatory authorities or of all the regulatory authorities of the region concerned.

5.   By 31 October 2023, and every three years thereafter, the Commission shall submit a report to the European Parliament and to the Council on ACER's involvement in the development and adoption of terms and conditions or methodologies for the implementation of network codes and guidelines adopted as delegated acts after 4 July 2019. Where appropriate, the report shall be accompanied by a legislative proposal to transfer or modify the necessary powers to ACER.

6.   Before approving the terms and conditions or methodologies referred to in paragraphs 2 and 3, the regulatory authorities, or, where competent, ACER, shall revise them where necessary, after consulting the ENTSO for Electricity, the ENTSO for Gas or the EU DSO entity, in order to ensure that they are in line with the purpose of the network code or guideline and contribute to market integration, non-discrimination, effective competition and the proper functioning of the market. ACER shall take a decision on the approval within the period specified in the relevant network codes and guidelines. That period shall begin on the day following that on which the proposal was referred to ACER.

7.   ACER shall carry out its tasks as regards the bidding zone review pursuant to Article 14(5) of Regulation (EU) 2019/943.

8.   ACER shall monitor the regional cooperation of transmission system operators referred to in Article 34 of Regulation (EU) 2019/943 and Article 12 of Regulation (EC) No 715/2009, and shall take into account the outcome of that cooperation when formulating its opinions, recommendations and decisions.

also move between articles