Duration of the permit-granting process for net-zero strategic projects

1.   The permit-granting process for net-zero strategic projects shall not exceed:

(a)

9 months for the construction or expansion of net-zero strategic projects with a yearly manufacturing capacity of less than 1 GW;

(b)

12 months for the construction or expansion of net-zero strategic projects with a yearly manufacturing capacity of 1 GW or more;

(c)

18 months for all necessary permits to operate a storage site in accordance with Directive 2009/31/EC.

2.   For net-zero strategic projects for which a yearly manufacturing capacity is not measured in GW, the permit-granting process shall not exceed 12 months.

3.   Where an environmental impact assessment is required pursuant to Directive 2011/92/EU, the step of the assessment referred to in Article 1(2), point (g)(i), of that Directive shall not be included in the duration for the permit-granting process referred to in paragraphs 1 and 2 of this Article.