Facultative Grounds for Exclusion

(1) Taking the principle of proportionality into account, public contracting authorities may at any point in the procurement procedure exclude an undertaking from participating in the procurement procedure if

1.  the undertaking has demonstrably breached applicable environmental, social or labour obligations in carrying out public contracts;

2.  the undertaking is insolvent, an insolvency proceeding or a comparable proceeding over the assets of the undertaking has been filed or opened, the opening of such a proceeding has been denied for lack of assets, the undertaking is in liquidation proceedings or has ceased to do business;

3.  the undertaking has demonstrably committed grave professional misconduct which renders its integrity questionable; Section 123(3) shall apply mutatis mutandis;

4.  the public contracting authority has sufficient indications that the undertaking has concluded agreements with other undertakings or engaged in concerted practices which have as their object or effect, the prevention, restriction or distortion of competition;

5.  a conflict of interest exists in the execution of the procurement procedure which could compromise the impartiality and independence of a person working for the public contracting authority in the executing of the procurement procedure and which cannot be effectively remedied by other, less intrusive measures;

6.  a distortion of competition results from the prior involvement of the undertaking in the preparation of the procurement procedure, and such distortion of competition cannot be remedied by other, less intrusive measures;

7.  the undertaking has produced significant or persistent deficiencies in the performance of a substantive requirement under a prior public contract or concession contract which led to an early termination, damages or other comparable sanctions;

8.  the undertaking has committed a serious misrepresentation or withheld information or is not able to submit the required evidence with respect to the grounds for exclusion or the selection criteria; or

9.  the undertaking

a)  has attempted to unduly influence the decision-making process of the public contracting authority;

b)  has attempted to obtain confidential information that may confer upon it undue advantages in the procurement procedure; or

c)  has negligently or intentionally provided misleading information that may have a material influence on the decision of the public contracting authority concerning the award decision, or has attempted to provide such information.

(2) Section 21 of the Posted Workers Act [Arbeitnehmer-Entsendegesetz], Section 98c of the Residence Act [Aufenthaltsgesetz], Section 19 of the Minimum Wage Act [Mindestlohngesetz], Section 21 of the Act to Combat Undeclared Work and Unlawful Employment [Schwarzarbeitsbekämpfungsgesetz] and Section 22 of the Act on Corporate Due Diligence Obligations in Supply Chains [Lieferkettensorgfaltspflichtengesetz] shall remain unaffected.